Roof and
waterproofing
specialists

125-133 Pollard Street
Manchester
M4 7JB

Report

14-20 Mirabel St, Cheetham Hill, Manchester M3 1DX

Cladding survey:

We were instructed by Scanlans to undertake a cladding integrity survey, and to carry out inspection and repairs over missing panels caused by recent wind damage and fixing failure. After initial inspection, we have found multiple point of catastrophic failure to over 30% of the panels with excessive movement, and the remaining panels all have abnormal movement. Our only recommendations, are to remove and re-fix every panel to guarantee future stability and a long term solution and to ensure protection of the public surrounding the building.

Highlighted areas labelled 1-26 represent days on site with excellent weather conditions with storage of all cladding panels permitted on adjacent balconies. (please note: this is a budgetary timescale based on the current information uncovered within the survey.

Men on site per day: 5.

Days on site: 26. (approx)

Budgetary cost: £52,000 + VAT

Please note: under high wind could detach from the building and cause danger to life. Due to the extent of failure identified, there is no short term solution and we recommend this is reviewed as soon as possible.


Document date: 26-09-2020